Structural steel beams for most of the north building roof have been installed. The metal roof pans will be installed next week. The installation of the structural steel beams on the south building roof will begin once the roof pans are installed on the north building.
Archives for September 2015
Planning and Facilities Fall 2015 Newsletter
Anne Arundel Hall Update
Wood beams for the Blackistone Room have been installed and water proofing of the exterior masonry is in progress. The north building masonry gable ends are installed and in progress in the south building. The west building attic slab and north building gable end cap beam will be placed this week. In addition, the geothermal wells are in the process of being drilled.